Commercial Roof Snow Load in Minnesota: When Does Roof Snow Need to Come Off?

9 min read Updated  By the East Metro Snow Removal team

Quick answer

Minnesota Rule 1303.1700 sets a 50 psf design ground snow load for every Twin Cities metro county, but that is the engineer's starting point, not your roof's capacity. Actual capacity depends on the building's design, age, drifts and drainage. If you see sagging, dropping sprinkler heads, doors that stick, new cracks or severe leaks, evacuate and call a structural engineer. Roof snow removal is work for experienced roofing crews with fall protection.

Key takeaways

  • Minnesota's design ground snow load is 50 psf in all metro counties and 60 psf in a listed group of northern counties.
  • Ground snow load is not roof capacity; find your roof's design snow load on the structural drawings or have an engineer determine it.
  • FEMA puts one foot of fresh snow at 3–21 psf and one foot of ice at about 57 psf, so depth alone says little.
  • Drifts at parapets, step-downs and rooftop units can load a roof far more heavily than the snow on open areas.
  • Ground crews handle drop zones, the snow that comes down, and ice at downspouts; roof work belongs to roofing pros.
In this guide
  1. What is the ground snow load in Minnesota?
  2. Why isn't the ground snow load the same as roof capacity?
  3. How much does snow on a roof weigh?
  4. Where do drifts load a commercial roof?
  5. What are the warning signs of roof overstress from snow?
  6. Who should remove snow from a commercial roof?
  7. What does the ground crew handle when roof snow comes down?
  8. How should a property plan for roof snow before winter?
  9. Frequently asked questions

What is the ground snow load in Minnesota?

Minnesota's design ground snow load is 50 pounds per square foot (psf) in most of the state, including every Twin Cities metro county, and 60 psf in a listed group of northern counties. The rule is Minnesota Rule 1303.1700, part of the State Building Code. Ramsey, Washington, Dakota and Hennepin counties are all 50 psf.

The 60 psf counties are Aitkin, Becker, Beltrami, Carlton, Cass, Clearwater, Cook, Crow Wing, Hubbard, Itasca, Kanabec, Kittson, Koochiching, Lake, Lake of the Woods, Mahnomen, Marshall, Mille Lacs, Morrison, Norman, Otter Tail, Pennington, Pine, Polk, Red Lake, Roseau, St. Louis, Todd and Wadena. If you manage property up north as well as in the metro, the design basis differs.

Ground snow load is the weight of snow on the ground surface that building designers use as the starting point for calculating roof loads. FEMA's Snow Load Safety Guide explains that ground snow load values in the national model codes represent about a 2 percent chance of being equaled or exceeded in any given year. That makes them a design basis, not a ceiling: real snow loads can exceed them in an extreme season.

This guide is general information for property and facility managers, not engineering advice. Decisions about a specific roof belong to a structural engineer who has reviewed that building.

Why isn't the ground snow load the same as roof capacity?

The ground snow load is only one input; an engineer turns it into a roof design load using factors specific to the building, and the building's actual capacity also depends on when it was designed, how it was built and how it has been changed since. FEMA lists the factors that go into a roof snow load: the ground snow load, the building's importance and occupancy, wind exposure, roof slope, roof shape, roof obstructions and the building's thermal condition. Two buildings next door to each other can have very different roof design loads.

Age matters a lot. FEMA notes that drifting loads were first incorporated into the BOCA code, used across much of the Midwest, in 1975, and that a building constructed 40 years ago may not have been designed for snow loads as they are understood today. Rooftop equipment added during a renovation may never have been checked against the roof structure either.

FEMA is blunt on one common shortcut: measuring the weight of snow on the ground and assuming the roof carries the same load is incorrect. Wind strips snow off some areas and piles it on others, and melt water collects at low points.

To find your roof's design snow load:

  1. Look at the construction drawings. FEMA notes that the design snow load can be determined from them; structural sheets typically list design loads in their general notes.
  2. If drawings are missing or unclear, hire a structural engineer before the season to determine capacity and set practical benchmarks for when snow should come off.
  3. Ask the engineer to identify drift zones and any areas that need closer watching.

How much does snow on a roof weigh?

Snow on a roof weighs anywhere from about 3 to 21 pounds per square foot per foot of depth when fresh, and ice is far heavier. Those figures come from FEMA's Snow Load Safety Guide. The range is wide because snow density varies so much: a foot of dry, fluffy January snow weighs a fraction of a foot of wet, heavy spring snow.

Roof coveringApproximate weight (FEMA)
1 ft of fresh, light, dry snowabout 3 psf
1 ft of fresh, wet, heavy snowabout 21 psf
1 inch of icea little less than 5 psf
1 ft of iceabout 57 psf

Depth alone tells you little. Snow settles, gets denser, and turns partly to ice as it melts and refreezes. FEMA notes that building codes account for light rain on snow but not heavy rainfall, and that a short rain can saturate snow and significantly increase the load. A layered roof of old snow, ice and new snow is the case engineers worry about most.

Seasons matter too. The Twin Cities averages 54.0 inches of snow a season, per MN DNR normals, but 2022–23 brought 90.3 inches, the third-snowiest season on record. Long cold stretches with little melt let roof snow accumulate storm after storm, which is when watching the roof and the building interior pays off.

Where do drifts load a commercial roof?

Drifts load a roof wherever wind can carry snow off one surface and drop it in a sheltered spot beside an obstruction or a change in height. FEMA explains that drifts often form on a lower roof in the wind shadow of higher portions of the building, and against obstructions such as high roof framing, rooftop equipment, parapets and adjacent buildings. The snow depth at those spots is greater than across the rest of the roof, so the load is greater there too.

Roof featureWhy snow builds up thereWhat to watch
Parapets on flat and low-slope roofsWind drops snow against the wallDeep drifts along the parapet line
Step-downs to a lower roofLower roof sits in the wind shadow of the higher oneDrifts and sliding snow on the lower roof
Rooftop units, screen walls and penthousesEquipment blocks the windDrifts on the downwind side
Skylights and ventsSmall obstructions catch driftsBuried skylights are also a fall-through hazard
Valleys and saw-tooth low pointsSnow collects where surfaces meetExtra depth and ice
Roof drains and low spotsMelt water pools if drains are blockedPonding, which concentrates load
Eaves on sloped roofsIce dams form as melt refreezesConcentrated load and falling ice

Drainage is part of snow load. FEMA describes ponding, melt water collecting at low points on roofs with poorly designed or blocked drainage, as a concentrated load and a potential hazard. Keeping roof drains, gutters and downspouts clear before and between storms is one of the simplest ways to reduce risk.

What are the warning signs of roof overstress from snow?

FEMA lists the common warning signs of an overstressed roof as sagging ceilings and sprinkler lines, sprinkler heads dropping below suspended ceilings, popping or creaking noises, sagging roof members, doors and windows that stop opening or closing, cracks in walls, severe leaks and water collecting where it shouldn't. Wood and steel structures may show noticeable deflection before they fail, which is why someone should be watching the interior during and after heavy snow.

FEMA's list of warning signs in wood, metal and steel buildings:

  1. Sagging ceiling tiles or boards, ceiling boards falling out of the grid, or sagging sprinkler lines and heads.
  2. Sprinkler heads deflecting below suspended ceilings.
  3. Popping, cracking and creaking noises.
  4. Sagging roof members, including metal decking or plywood sheathing.
  5. Bowing truss bottom chords or web members.
  6. Doors or windows that can no longer be opened or closed.
  7. Cracked or split wood members.
  8. Cracks in walls or masonry.
  9. Severe roof leaks.
  10. Excessive water accumulating at non-drainage locations on low-slope roofs.

If any of these appear, FEMA's guidance is to evacuate the building promptly and contact a qualified design professional, such as a professional engineer, for a detailed structural inspection. Do not send people onto a roof that may be failing. If there is any concern that snow loads may cause a collapse, FEMA says to stop all removal work and evacuate.

Assign someone to walk the interior during heavy-snow periods, especially in warehouses, big-box retail and gyms with long spans, and give them this list and a phone number to call.

Who should remove snow from a commercial roof?

Roof snow should be removed by an experienced, insured commercial roofing contractor working under a plan set with a structural engineer, using fall protection and a safety plan that meets OSHA rooftop requirements. FEMA's Snow Load Safety Guide recommends a professional roofing contractor with experience removing roof snow because of their familiarity with safety protocols. This is not a job for a lot-plowing crew with shovels and ladders.

The risks are specific. Falls from roof edges, through buried skylights, and from ladders are the obvious ones. Damage to the roof membrane is the costly one: FEMA advises leaving at least 2 inches of snow on the roof, avoiding mechanical snow removal equipment and sharp tools such as picks, and using plastic shovels rather than metal.

The removal sequence matters for the structure, too. FEMA's guidance:

  • Remove drifted snow first, at building elevation changes, parapets and around equipment.
  • Then start on the remaining snow from the center of the roof.
  • Remove snow in the direction of the primary structural members to avoid unbalanced loading.
  • Don't stockpile snow anywhere on the roof.
  • Drop snow only into designated areas on the ground, away from exits, fire escapes, downspouts, vents and equipment.
  • Keep someone on the ground to keep people out of the area where snow and ice are falling.

Line up a roofing contractor before winter. FEMA notes that contractors are in high demand and hard to find once a storm starts, which is exactly when you'd need one.

What does the ground crew handle when roof snow comes down?

The ground crew handles everything at pavement level: closing off the drop zones below the roof, clearing and hauling the snow that comes down, and managing the ice that forms at downspouts, eaves and canopies. On a big roof-clearing day, that is a lot of snow landing on a lot and walks that may already be full. Coordinating the two crews keeps entrances open and keeps roof snow out of places it shouldn't go.

Ground-level work to plan for:

  • Drop zones. Cone or barricade the area below the roof edge while crews work, and keep foot traffic and vehicles out.
  • Designated landing areas. FEMA recommends choosing ground storage areas for roof snow before the season, away from entrances, exits, canopies and building equipment. Put them on the snow site map.
  • Clearing and hauling. Roof snow often lands on walks and drive lanes and has to be cleared the same day. If the lot's stack zones are full, it has to be hauled. Our snow hauling and relocation page explains how that's scoped.
  • Downspouts and drip lines. Melt from roofs that discharges across walks refreezes every night. Treat those paths on refreeze patrols, and ask whether downspouts can be extended or rerouted. See our guide to commercial ice management.
  • Icicles and canopies. Watch entries under eaves and canopies, where falling ice is a hazard to pedestrians.
  • Drains. Keep storm drains and downspout outlets at grade open so melt water can leave the site.

East Metro Snow Removal bids the ground-level work, meaning parking lots, sidewalks, entrances, salting and hauling, and does not bid roof snow removal. Our sidewalk and entrance clearing page covers the walks, entries and ramps that roof snow tends to land on.

How should a property plan for roof snow before winter?

Plan for roof snow the same way you plan for lot snow: before the season, in writing, with roles assigned. FEMA recommends a Snow Event Response Plan for major facilities, such as manufacturing buildings, warehouses and big-box retail, covering both preventative steps and what to do during a storm. Assigning those tasks before the season, FEMA notes, reduces confusion when a storm hits and helps ensure nothing is overlooked.

A pre-season roof snow checklist, drawn from FEMA's guidance:

  1. Find the roof's design snow load on the drawings, or have a structural engineer determine it.
  2. Ask the engineer to identify drift zones and set benchmarks for when snow should be removed.
  3. Clear roof drains, gutters and downspouts, and fix deficiencies found in the roof inspection.
  4. Mark rooftop hazards such as skylights, conduits, gas lines and vents with flags or a similar system so they can be found under snow.
  5. Retain a roofing contractor for snow removal, or decide whether in-house staff will do it with an OSHA-compliant safety plan.
  6. Choose ground landing areas for roof snow and add them to the snow site map.
  7. Add the engineer and roofing contractor to the storm-night contact tree.

Our guides to the pre-season site walk and snow site map and the winter storm checklist for property managers show where roof snow fits into the rest of your winter plan.

Frequently asked questions

Is 50 psf the roof snow load for buildings in St. Paul and Minneapolis?

No. Fifty psf is the design ground snow load that Minnesota Rule 1303.1700 sets for metro counties. Engineers convert it into a roof design load using the building's exposure, slope, shape, thermal condition, use and obstructions, and they add drift loads. Your roof's design snow load is on the structural drawings or can be determined by an engineer.

How much snow can a flat commercial roof hold?

There is no single answer, because it depends on the roof's design snow load, its condition and how the snow is distributed. FEMA puts fresh snow at about 3 to 21 psf per foot of depth, so the same depth can weigh seven times more when wet. A structural engineer can turn your roof's capacity into practical depth benchmarks.

Can our parking lot snow contractor clear the roof too?

Roof snow removal is different work: fall protection, roof access, membrane protection and a removal sequence based on the structure. FEMA recommends an experienced professional roofing contractor. A lot contractor can coordinate on the ground, clearing drop zones and hauling the snow that comes down, but the roof crew and engineer should run the roof.

Should all the snow be removed from a flat roof?

No. FEMA advises leaving at least 2 inches of snow on the roof, because scraping to the membrane can damage the roofing and cause leaks. The goal is to reduce the load, starting with drifts at parapets, step-downs and equipment, not to get the roof bare.

Are older buildings more at risk from roof snow?

They can be. FEMA notes that drift loads only entered the BOCA code in 1975 and that buildings designed decades ago may not reflect today's understanding of snow loads. Rooftop equipment added in later renovations may also never have been checked. Older buildings with long-span roofs are good candidates for a pre-season engineering review.

Does rain on top of snow make a roof more dangerous?

It can. FEMA explains that building codes account for light rain on snow but not heavy rainfall, and that a short rain can soak into the snowpack and significantly increase its weight. When rain is forecast on a deep snowpack, watch the interior for warning signs and check that roof drains are open.

Sources & further reading

Prices on this site are planning ranges, not quotes. Rules change: the city or agency page is always the authority. Nothing here is legal or insurance advice.

Free · No obligation · Commercial only

Get a written commercial snow bid

One form, one free written bid for your property. Every bid we write spells out:

  • A site mapPlow zones, stacking areas, no-stack zones and hazards, marked before the first storm.
  • Trigger depths & service levelsWhen service starts, zero-tolerance areas, and what “done” means.
  • Completion windowsTarget open-by times for lots, walks and entrances.
  • A salt & ice planPre-treat, deicer choice by pavement temperature, and re-treat rules.
  • Pricing you can compareSeasonal, per-push, per-event or hourly, priced side by side if you want.
  • DocumentationHow every visit is logged so you have a record.
Services to bid

Free and no obligation. Commercial properties only: HOAs, multifamily, retail, office, industrial, medical, churches and schools.

Get a free commercial snow bid